Job costing for small contractors
Short answer: Job costing means recording the real labor, material and subcontractor costs of each job and comparing them with your estimate. It shows you which jobs, customers and types of work actually make money.
What to record on every job
- Contract amount: the price you agreed, plus approved change orders.
- Labor hours and cost: who worked, how many hours, at what loaded rate.
- Materials: receipts and supplier invoices, matched to the job, not to the month.
- Subcontractors, rentals, permits and disposal.
- Your estimate for each of the above, so you can compare line by line.
The formulas
- Job cost = labor + materials + subcontractors + other direct costs
- Gross profit = contract amount − job cost
- Gross margin % = gross profit ÷ contract amount
- Variance = actual cost − estimated cost (positive means you overspent)
Worked example
| Line | Estimate | Actual | Variance |
|---|---|---|---|
| Materials | $2,900 | $3,100 | +$200 |
| Labor | $2,150 | $2,400 | +$250 |
| Subcontractor | $900 | $900 | $0 |
| Job cost | $5,950 | $6,400 | +$450 |
The contract was $8,500. Estimated gross profit was $2,550, a 30% margin. Actual gross profit was $2,100, which is a 24.7% margin. The job still made money, but the labor and material overruns took more than five points of margin. If this keeps happening on the same type of work, the fix is in the next estimate, not in working harder.
How often to check
Update costs weekly while a job runs. A job that is 30 percent over budget at the halfway point can still be fixed. One that is found over budget at the final invoice cannot.
Common mistakes
- Counting your own labor at zero. Pay yourself a loaded rate on the job, or the margin is fictional.
- Putting materials on the job only when the statement arrives, so costs land in the wrong month.
- Forgetting approved change orders, which makes a healthy job look like a loss. See change orders.
Frequently asked questions
What is job costing in construction?
It is tracking the real labor, material and subcontractor costs of each job and comparing them with the estimate to see profit and variance.
How do I calculate gross profit margin on a job?
Subtract the total job cost from the contract amount, then divide the result by the contract amount.
Do I need accounting software for job costing?
No. A spreadsheet with a line per cost and a column for the estimate works well for a small contractor, as long as you update it weekly.
Spreadsheets that do this for you
Each pack includes a job costing profit dashboard that compares estimate and actual and shows margin per job. Each pack is US$19, one payment, Excel and Google Sheets, with a quote or estimate builder, daily log and change orders, a job costing dashboard and a tax set-aside tracker.
- Plumber Pack for plumbers
- Electrician Pack for electricians
- HVAC Pack for HVAC techs
- Handyman Pack for handymen
- Painter Pack for painters
- Flooring Pack for flooring installers
- Roofing Pack for roofers
- Snow & Landscaping Pack for snow removal and landscaping crews
- General Contractor Kit for general contractors and builders
More guides
- How to price a contractor job: Direct costs, overhead and profit, with a worked example you can copy.
- Markup vs margin for contractors: Why a 25% markup is only a 20% margin, with a conversion table.
- Change order template for contractors: Get paid for extra work: what a change order must say.