Change order template for contractors

By The Money Reset · Updated November 3, 2026

Short answer: A change order is a short written agreement, signed before you do the work, that records what changed, what it costs and how it affects the schedule. Without one, extra work is often unpaid.

What every change order should include

  1. Job name, address and the original contract date.
  2. A change order number and today's date, so they run in order: CO-001, CO-002 and so on.
  3. A plain description of the change: what is being added, removed or substituted, and where.
  4. The price, as an add or a credit, with the new contract total.
  5. The schedule impact: extra days, or "no change".
  6. Payment terms: when it is billed.
  7. Signatures and dates from the customer and from you.

Example

The homeowner asks for two extra outlets in the kitchen after the contract is signed.

LineAmount
Materials: boxes, wire, outlets, covers$85.00
Labor: 3 hours at $45 loaded$135.00
Cost$220.00
Price for a 25% margin: $220 ÷ 0.75$293.33

You would round it to a clean figure such as $295, write one sentence describing the work, add "no schedule change", and get a signature. The new contract total goes at the bottom.

Habits that keep you paid

Rules about what makes a change order binding differ by state, province and contract, so ask a local professional if a large job depends on it. This is general information, not legal advice.

Frequently asked questions

Do I need a change order for small extra work?

Yes, a short one. Even a text message that states the work, the price and the customer's yes is better than nothing, and it protects you if the customer later disagrees.

Can the customer pay for a change order separately?

Yes. Many contractors bill change orders with the next progress payment or the final invoice. State the terms on the change order.

What if the customer will not sign?

Pause the extra work until they agree. Doing it for free to avoid an awkward conversation is the most common way contractors lose margin.

Spreadsheets that do this for you

Each pack includes a daily log and change order sheet that numbers them, totals them and carries them into job costing. Each pack is US$19, one payment, Excel and Google Sheets, with a quote or estimate builder, daily log and change orders, a job costing dashboard and a tax set-aside tracker.